Summary of Estimate of Probable Costs
The following cost estimate is based on the plan for the Phase One Plan project scope. Click on “Phase One Plan” in the site menu for a plan view of where these items are located on this site.
Please Note: Cost data associated with the development of this master plan was determined in 2016. Updated cost data is available on the Palos Verdes Peninsula Unified School District website, MEASURE PV Information, under “Status of PVPUSD Facilities”.
Phase One Plan Probable Costs
Valmonte-Sunrise Early Learning Academy – Phase One Plan
PI# | Scope Description | Quantity | × | Unit Cost | = | Cost | Total Cost | ||
---|---|---|---|---|---|---|---|---|---|
Hard Construction Costs | |||||||||
Site Work | |||||||||
Site Work Costs | 0 | ||||||||
New Construction | |||||||||
New Construction Costs | 0 | ||||||||
Reconfiguration | |||||||||
Reconfiguration Costs | 0 | ||||||||
Modernization | |||||||||
![]() |
Classroom Building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. | 2708 | SF | × | 235 | per SF | = | 636380 | 636,380 |
![]() |
Classroom Building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. | 5406 | SF | × | 235 | per SF | = | 1270410 | 1,270,410 |
![]() |
Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. | 5880 | SF | × | 235 | per SF | = | 1381800 | 1,381,800 |
![]() |
MPR, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. | 4769 | SF | × | 235 | per SF | = | 1120715 | 1,120,715 |
![]() |
Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. | 8252 | SF | × | 235 | per SF | = | 1939220 | 1,939,220 |
Modernization Costs | 6,348,525 | ||||||||
Demolition | |||||||||
Demolition Costs | 0 | ||||||||
Miscellaneous | |||||||||
Miscellaneous Costs | 0 | ||||||||
Hard Construction Cost Subtotal | 6,348,525 | ||||||||
Soft Project Costs | 27.00 | % | of Hard Construction Costs | 1,714,102 | |||||
Hard Construction Cost + Soft Project Costs Subtotal | 8,062,627 | ||||||||
Escalation | 4 | years | @ | 4.00% | per year | = | 16.99% | 1,369,506 | |
Overall Contingency | 10.00% | of total | = | 11.11% | 1,048,015 | ||||
Total Probable Phase One Plan Costs for Valmonte-Sunrise Early Learning Academy |
10,480,148 |