Silver Spur Elementary School

Estimate of Probable Costs

Summary of Estimate of Probable Costs

The following cost estimate is based on the plan for the Phase One Plan project scope (updated in 2024). Click on “Phase One Plan” in the site menu for a plan view of where these items are located on this site.

Phase One Plan Probable Costs

Silver Spur Elementary School – Phase One Plan

PI# Scope Description Quantity × Unit Cost = Cost Total Cost
Hard Construction Costs
Site Work
S1 Replace site utilities 10.26 AC × 84942 per AC = 871505 871,505
Site Work Costs 871,505
New Construction
New Construction Costs 0
Reconfiguration
Reconfiguration Costs 0
Modernization
M1 Media Center, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 1920 SF × 395 per SF = 758400 758,400
M2 Classroom and Specialty Classrooms, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 6441 SF × 395 per SF = 2544195 2,544,195
M3 Classrooms, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 6441 SF × 395 per SF = 2544195 2,544,195
M4 Kindergarten classrooms, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 6307 SF × 395 per SF = 2451765 2,451,765
Modernization Costs 8,298,555
Demolition
Demolition Costs 0
Miscellaneous
Miscellaneous Costs 0
Hard Construction Cost Subtotal 9,170,060
Soft Project Costs 27.00 % of Hard Construction Costs 2,475,916
Hard Construction Cost + Soft Project Costs Subtotal 11,645,976
Escalation 5 years @ 4.50% per year = 24.62% 2,867,029
Overall Contingency   10.00% of total = 11.11% 1,612,556
Total Probable Phase One Plan Costs for
Silver Spur Elementary School
16,125,561