Ridgecrest Intermediate School

Estimate of Probable Costs

Summary of Estimate of Probable Costs

The following cost estimate is based on the plan for the Phase One Plan project scope (updated in 2024). Click on “Phase One Plan” in the site menu for a plan view of where these items are located on this site.

Phase One Plan Probable Costs

Ridgecrest Intermediate School – Phase One Plan

PI# Scope Description Quantity × Unit Cost = Cost Total Cost
Hard Construction Costs
Site Work
S1 Replace site utilities 20 AC × 84942 per AC = 1698840 1,698,840
Site Work Costs 1,698,840
New Construction
New Construction Costs 0
Reconfiguration
Reconfiguration Costs 0
Modernization
M1 Specialty Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 9294 SF × 395 per SF = 3671130 3,671,130
M2 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 11376 SF × 395 per SF = 4493520 4,493,520
M3 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 10780 SF × 395 per SF = 4258100 4,258,100
M4 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 12232 SF × 395 per SF = 4831640 4,831,640
Modernization Costs 17,254,390
Demolition
Demolition Costs 0
Miscellaneous
Miscellaneous Costs 0
Hard Construction Cost Subtotal 18,953,230
Soft Project Costs 27.00 % of Hard Construction Costs 5,117,372
Hard Construction Cost + Soft Project Costs Subtotal 24,070,602
Escalation 5 years @ 4.50% per year = 24.62% 5,925,747
Overall Contingency   10.00% of total = 11.11% 3,332,928
Total Probable Phase One Plan Costs for
Ridgecrest Intermediate School
33,329,277