The following cost estimate is based on the plan for the Phase One Plan project scope (updated in 2024). Click on “Phase One Plan” in the site menu for a plan view of where these items are located on this site.

Phase One Plan Probable Costs

Point Vicente Elementary School – Phase One Plan

PI# Scope Description Quantity × Unit Cost = Cost Total Cost
Hard Construction Costs
Site Work
S1 Replace site utilities 10.4 AC × 84942 per AC = 883397 883,397
Site Work Costs 883,397
New Construction
New Construction Costs 0
Reconfiguration
Reconfiguration Costs 0
Modernization
M1 Classroom building Media Center and Kids Club, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4820 SF × 395 per SF = 1903900 1,903,900
M2 Classroom and Specialty Classroom Building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4820 SF × 395 per SF = 1903900 1,903,900
M3 Classroom and Specialty Classroom Building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4820 SF × 395 per SF = 1903900 1,903,900
M4 Kindergarten building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 3032 SF × 395 per SF = 1193690 1,193,690
Modernization Costs 6,905,390
Demolition
Demolition Costs 0
Miscellaneous
Miscellaneous Costs 0
Hard Construction Cost Subtotal 7,788,787
Soft Project Costs 27.00 % of Hard Construction Costs 2,102,972
Hard Construction Cost + Soft Project Costs Subtotal 9,891,759
Escalation 4 years @ 4.00% per year = 16.99% 1,680,200
Overall Contingency   10.00% of total = 11.11% 1,285,773
Total Probable Phase One Plan Costs for
Point Vicente Elementary School
12,857,732