Montemalaga Elementary School

Estimate of Probable Costs

Summary of Estimate of Probable Costs

The following cost estimate is based on the plan for the Phase One Plan project scope (updated in 2024). Click on “Phase One Plan” in the site menu for a plan view of where these items are located on this site.

Phase One Plan Probable Costs

Montemalaga Elementary School – Phase One Plan

PI# Scope Description Quantity × Unit Cost = Cost Total Cost
Hard Construction Costs
Site Work
S1 Replace site utilities 9.7 AC × 84942 per AC = 823937 823,937
Site Work Costs 823,937
New Construction
New Construction Costs 0
Reconfiguration
Reconfiguration Costs 0
Modernization
M1 Kindergarten, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 2120 SF × 395 per SF = 837400 837,400
M2 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4820 SF × 395 per SF = 1903900 1,903,900
M3 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4820 SF × 395 per SF = 1903900 1,903,900
M4 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4820 SF × 395 per SF = 1903900 1,903,900
M5 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 6220 SF × 395 per SF = 2456900 2,456,900
Modernization Costs 9,006,000
Demolition
Demolition Costs 0
Miscellaneous
Miscellaneous Costs 0
Hard Construction Cost Subtotal 9,829,937
Soft Project Costs 27.00 % of Hard Construction Costs 2,654,083
Hard Construction Cost + Soft Project Costs Subtotal 12,484,020
Escalation 5 years @ 4.50% per year = 24.62% 3,073,340
Overall Contingency   10.00% of total = 11.11% 1,728,596
Total Probable Phase One Plan Costs for
Montemalaga Elementary School
17,285,956